Detailed Linkage Information Released

London & Cambridge have released detailed information in relation to the linkage works, which start on February 13th. 

The attached picture shows the work carried out and is the latest, current version of the plans. We do have more detailed plans, detailing each phase of the works, if you would like to view these please get in touch. 

Important dates to note

Phase 1A – Monday Feb 13th – Works commence, setup car park diversion. 

Phase 1B – Friday 24th Feb – Set up and erect fencing, replace road markings.

Phase 2A – Thu 2nd March – Landscaping, new lighting, install drainage.

                     Thu 23rd March – Open completed car park. 

Phase 2B – Thu 16th March – Remove existing paving from walkway to Newport Road. 

Phase 3A – Wed 5th April – Lay new paving (walkway) resurfacing

Phase 3B – Fri 14th April – Lay Ramps, Road resurfacing. 

Completion – Tue 25th April

 

If you would like further information, please get in contact with us, where we can provide information on detailed plans and dates. 