* Updated Projected Dates for Asda Site
We have had confirmation from the contractors ISG on projected dates for the works being carried out on the Asda Development.
26th June – Steel frame for store due to be delivered – Delayed slightly from original date of 23rd June
(May cause some disruption to traffic during the day)
4th August – Woodstock way will be closed to the public and new link road opened
3rd October – Estimated completion date of works by ISG (contractor)
End of October/Early November – Asda due to open new store
These dates are subject to change, dependant on works and delays, we will endeavour to update the website as soon as we receive information.